Step 1:
Organize parts A to H into separate areas/piles
so you can easily find the part being called for in steps 2
through 10.
Step 2:
Slide two (2) Part C clamps on each of the two
stand base bars [Part B1 (2 sets)]. One part C clamp will face
vertical, and the other Part C clamp will face horizontal. Use
Parts F screws and nuts to fasten all Part C
clamps.
Install (2)
each rubber feet Part A1 to the ends of each stand base bar (part
B1). The flat part of rubber feet A1 faces the floor. Install (1)
horizontal bar (Part B2) to the horizontal clamp (Part C) of each
of the stand base assemblies (B1/C/A1
combination).
Step 3:
Insert (2) vertical bars (Part B2) to the
remaining B1/C/A1 base assembly combinations (vertical). Insert
(2) part C clamps to the ends of (1) bar part B2. Slide this
combination on the (2) vertical bars Part
B2.
Step 4:
Slide (1) Part D clamp down the left hand
vertical bar (B2). This will be used later for your yellow
snare-drum pad. Slide (3) part D clamps on the remaining
horizontal bar part B2. Install (2) part C clampsto the ends of
this bar part B2. Slide this combination onto the vertical bars
Part B2. Adjust the upper bar combination to be almost to the top
(about 4 to 5 inches down from top). Slide the remaining Part D
clamp on the left vertical bar Part B2. This will be used later
for your red Hi-Hat pad.
Step 5:
Install a rubber cap part A2 to the top of each
of the vertical bars part B2. Tighten all bar-connection screws
and be sure the rack is stable. Tighten all screws for parts C
clamps. Tighten all screws for Part D clamps until they are snug,
but can be moved and turned.
Step 6:
Install the Master Controller (SV-BOX) by using the Part G
clamp to mount the Part SV-BOX to the lower (center) horizontal
bar Part B2 using (4) Part H screws. The multiple connection ports
of the Master Controller should face up for easy access. Adjust
and tighten. Note: Do not tighten the screws
too hard.
Step 7:
Each of the Percussion Pads are color coded. Insert (10) Part
A3 to each end of (5) drum-arm rods Parts B3. Attach (5) Part E
adjustable brackets to each of the percussion pads (one part SD-8
and 4 part SD-5) using Part F screws and nuts. The gear side of
Part E djustable bracket matches with the gear side of the pads
(Parts SD-8 & SD-5). Tighten finger tight only at this
point.
Step 8:
Referring to Figure 1, slide (5) Part B3 drum-arm rods into
the hole of each of the remaining Part D clamps. Tighten finger
tight only at this point. Use the diagram above for
reference.
Step 9:
Referring to Figure 1, note that Percussion Pad
Part SD-8 (hitop) has an extra port connection and a pressure
switch/button, which is used to control ˇ§chokeˇ¨ (Tone-Mute) of
cymbal 5 (pad 5). During drum play this switch can be pressed by
the drummersˇ¦ finger to activate the feature. The SD-8 percussion
pad is color coded purple and should be mounted on the right of
the drum stand. Install each of the Part SD- 8/SD-5 Percussion Pad
to the rod/clamp (B3/D) combinations. Tighten the screws when
complete (do not over-tighten).
Step 10:
The sound made by each drum head is based on
the port number of the SV-BOX Master Controller. Connect one end
of each of (7) audio source cables to each SD-8/SD-5 percussion
pads and BD-6 foot pedal. Percussion pad SD-8 has (2) connections.
Connect the other ends of the audio source cables to the ports of
the Master Controller (SVBOX) as per Table
1.